Quick answer: The Canadian CCUS investment tax credit has different rates for direct air capture, other capture equipment, and transportation, storage or use. A 60% headline does not apply to an entire project budget. Before treating an expected credit as part of a financing plan, classify each expenditure, confirm the claimant and project evaluation, and model the cash needed before a refund arrives.
Disclaimer: This article is general information only and is not tax, legal or accounting advice. Tax rules change and depend on your situation. Speak with a qualified accountant or tax advisor before making any purchase or filing decision. Mehmi Financial Group does not provide tax advice.
Key takeaways
- Separate the engineering estimate from the tax-qualified expenditure schedule.
- Use the applicable category and expenditure date for each line.
- Assign responsibility for labour compliance and supporting records before construction.
- Fund supplier obligations without assuming a particular refund date.
Which rate belongs in the equipment budget?
The current Income Tax Act and CRA calculation page show regular rates of 60% for qualified direct air capture expenditures, 50% for other qualified capture expenditures, and 37.5% for qualified transportation, storage or use expenditures incurred from 2022 through 2035. The corresponding rates for 2036 through 2040 are 30%, 25% and 18.75%. These are category rates, subject to the qualification and labour rules. They are not a percentage of every dollar spent developing a site.
Have the engineering team label the intended function of each equipment package. A purchase order described only as a carbon capture system may combine capture equipment, transport components, services and preliminary work. A finance team cannot reliably assign one rate to that invoice without a defensible allocation. Ask for a component schedule before approving the supplier's billing format.
Keep the estimate's version date beside the expenditure schedule. Older presentations may show an earlier phase-down date. For a purchase decision, ask the tax adviser to use the legislation and current administrative guidance applicable to the expenditure, then retain the source and date in the approval file.
Confirm the project before calculating the benefit
CRA describes project qualification as a separate test. The project plan must support the required capture period and eligible-use conditions, and an initial NRCan evaluation must include a verified property list. A temporary demonstration and a commercial facility can therefore require different analysis even if they use similar machinery. Treat the supplier's technical description as evidence to examine, not a determination that the buyer qualifies.
Start an eligibility register with four columns: equipment identifier, engineering function, supporting document and unresolved question. Match the identifiers to invoices and drawings. If the design changes, keep both versions and identify the affected property. This avoids a late reconciliation where the tax team has a different equipment list from the construction manager.
CRA's readiness guidance also identifies a project determination from CRA and an NRCan project code. Ask who will obtain each item, who receives correspondence and who can approve changes to the application. A parent company, operating subsidiary and project partnership may have different responsibilities. The entity paying an invoice should not assume it is automatically the entity entitled to the credit.
A worked budget with mixed categories
Consider a hypothetical project with $4 million of qualified non-direct-air capture expenditure and $2 million of qualified transportation or storage expenditure. Assume the spending dates fall in the regular-rate period, the full amounts qualify, all required elections and labour conditions are satisfied, and no assistance or allocation adjustment changes the base. This is arithmetic for planning, not a tax determination.
| Budget line | Assumed qualified amount | Illustrative rate | Calculated amount |
|---|---|---|---|
| Other capture equipment | $4,000,000 | 50% | $2,000,000 |
| Transportation or storage | $2,000,000 | 37.5% | $750,000 |
| Combined | $6,000,000 | Mixed categories | $2,750,000 |
Applying 60% to the entire $6 million would produce $3.6 million, overstating this simplified category calculation by $850,000. Add a separate $500,000 of preliminary or otherwise excluded project costs and the total funding need becomes $6.5 million, while the assumed credit calculation remains $2.75 million. The long-run net cost and the cash required during construction are different amounts.
Now suppose $4 million of supplier payments falls due before any credit proceeds are received. The funding plan still needs to cover that $4 million when due. A projected credit may support later repayment if the financing agreement allows it, but it cannot pay an invoice before it becomes available. Show a delayed-refund case alongside the expected case and identify the source of any additional interest or extension costs.
Build an expenditure file that survives changes
For each purchase package, retain the signed contract, itemized invoice, payment evidence and technical description. Link installation and commissioning costs to the relevant property. Keep preliminary studies in their own ledger rather than blending them into equipment purchases. Ask the adviser to resolve treatment before closing the accounting period.
CRA's qualification guidance excludes preliminary work activities from qualified expenditures and describes specific capital-cost adjustments. It also addresses an amount remaining unpaid 180 days after the tax year ends. These details make the invoice date alone an unreliable planning shortcut. Your accountant should reconcile the legal obligation, actual payment and relevant tax-year treatment.
A change order needs the same discipline as the original order. Record whether it replaces equipment, adds capacity, changes the capture process or pays for a different service. Ask the engineering and tax teams to sign off on the revised classification. When a project crosses reporting periods, a small undocumented substitution can complicate several schedules later.
Labour requirements need an owner
Electing to meet the applicable labour requirements is part of accessing regular rates. The rules cover prevailing wages and apprenticeship requirements, with their own scope and exceptions. A decision not to elect can reduce the credit rate by ten percentage points. An election followed by non-compliance raises separate consequences; it should not be treated as a simple optional discount.
Before selecting contractors, ask how records will be delivered and retained. Identify who checks covered workers and work sites, who handles subcontractor information, and who follows up when a record is missing. A promise in a tender submission is useful only if the project can substantiate compliance later.
Include the record requirements in the procurement discussion while contractors can price and organize the work. Keep access to those records after completion and after a contractor leaves the site. The finance team's model should flag unresolved labour assumptions rather than silently using the highest rate.
Financing questions before signing
Give a potential funder the equipment scope, construction schedule and cash forecast. Ask which assets and costs it will consider, how draws are approved, and whether commissioning is required before repayment begins. Specialized process equipment may need a different review from standard movable machinery. Mehmi cannot establish product availability from a tax-credit calculation alone.
If leasing is proposed, obtain advice on which entity can claim the relevant credit and how the contract affects that result. Do not carry a purchaser's assumed credit into a lease model unchanged. Ask for the ownership documents and payment schedule to be reviewed together.
Also ask what happens if the expected credit is smaller or arrives later. Review mandatory repayment clauses, permitted prepayments, fees and the ability to extend a construction facility. A useful quote identifies the consequences of a delay in dollars and dates. It does not simply describe the credit as security.
Before authorizing the equipment order
- Reconcile the current design to the property and invoice lists.
- Confirm the claimant and which advisers own the technical and tax reviews.
- Separate qualified, excluded and unresolved expenditures.
- Document the labour election and recordkeeping plan.
- Assign each supplier payment to a committed funding source.
- Test a reduced-credit case and a later-refund case separately.
- Record approval conditions and the person responsible for clearing them.
Keep the register usable after commissioning. The related carbon capture equipment guide covers the broader equipment context; this page focuses on matching credit categories to a funding schedule. Neither replaces a project-specific tax opinion.
Related guides
- Equipment financing
- Alberta carbon capture incentives
- Check the Ontario manufacturing credit rules
- Clean Manufacturing ITC Canada
- In depth: Clean Economy Investment Tax Credits in Canada: Equipment Guide
Frequently asked questions
Does every carbon capture purchase receive 60%?
No. The 60% regular rate relates to qualified direct air capture expenditures within the applicable dates. Other capture and transportation, storage or use categories have different rates. Project qualification, expenditure allocation and labour conditions must also be addressed.
Can a projected refund replace the down payment?
Only a written financing arrangement can establish what funds are required at closing. An expected refund is not cash already available. Model supplier deposits and construction payments independently, then show any later credit proceeds as a separate event.
Who confirms equipment qualification?
NRCan handles technical evaluation and property verification within the process, while CRA administers the tax claim and related determinations. Engage advisers who can coordinate the engineering record with the corporate return rather than relying on the supplier's marketing description.
Should we finance the whole project as equipment?
Prepare separate requests for equipment and other costs where appropriate. Preliminary work, ongoing operations and construction contingencies can have different eligibility and funding treatment. Ask about product fit before assuming one facility will cover every line.
Tools and next steps
Prepare the asset quotation and a cash schedule before requesting terms. The equipment application document guide helps organize the supporting file. Keep uncertain costs separate so an estimate cannot be mistaken for committed funding.
Mehmi Financial Group works with over 50 lenders. Product fit and approval depend on the application and equipment. For this process, a startup needs six or more months of revenue in bank statements. Contact Mehmi or call 1-833-863-4644 to discuss the financing request.
Disclaimer: This article is general information only and is not tax, legal or accounting advice. Tax rules change and depend on your situation. Speak with a qualified accountant or tax advisor before making any purchase or filing decision. Mehmi Financial Group does not provide tax advice.
Sources
Primary sources reviewed November 12, 2026.
- Income Tax Act section 127.44
- CRA: calculating the CCUS credit
- CRA: qualifying projects and expenditures
- CRA: getting ready to claim
By Jodhbir Mehmi. Read our editorial standards.
